Our company built the 149 MW power plant with a coal fired circulating
fluidized bed boiler at Itoigawa Power Station of Taiheiyo Cement
Co., an independent power producer for Tohoku Electric Power Co.
Inc. The power plant was commissioned in July 2001, and has been
operated successfully more than one year since then, responding
to the cyclic change in power demand each day. The performance of
the circulating fluidized bed boiler has been proved satisfactory
for commercial power generation. This paper reports the boiler plant
design and the performance of the power plant as well as the boiler.
|